oak

Project Recap

Miles: 261.6
Pipe: 30”, .441” w.t.
Kick-off Location: Sonora, TX
End of Survey: Three Rivers, TX
Start Date: November 2018
Completion Date: October 2019
Construction Duration: 11 Months

Project Details

Pumpco built this project with 2 spreads.  A rock spread and a dirt spread.  The Rock spread was approximately 115 miles which consisted of 85 miles of solid rock.  Pumpco self-performed the ditch excavation with their own rock saw ditchers.  The rock spread was built in 11 months.  The dirt spread was 146.6 miles and was build in 8 months.  The dirt spread was welded up utilizing automation.