lonestar

Project Recap

Miles: 267
Pipe: 24”, .353” w.t. QRL
Kick-off: Location Midland, TX
End of Survey: Morgan, TX
Automated 195 Miles out of 267 Miles
Start Date: September 2015
Projected Completion Date: March 2016
Construction Duration: 7 Months

Project Details

In preparation for large scale projects on the horizon, the Pumpco Team elected to automate the majority of the Lone Star Express Project. In efforts to maximize efficiency and insure seamless construction for future projects, Pumpco automated more then two thirds of this project. All of these efforts were successful while completing Pumpco’s portion of the Lone Star Express in just under 7 months.