Pumpco, with the largest and most modern fleet of rock ditching machines was able to complete Spread 2 & Spread 3 with one mainline spread in 8 months.  Pumpco utilized a ditcher fleet which included 26 ditchers that can dig up to 60-72” wide x 10’ deep in solid rock conditions for 80 of 127 miles.

Project Recap: Spread 2

Miles: 62.32
Pipe: 42”, .600” w.t., QRL
Kick-off Location: Rankin, TX
End of Survey: Ozona, TX
Start Date: November 2018
Completion Date: July 2019
Construction Duration: 8 Months

Project Recap: Spread 3

Miles: 64.75
Pipe: 42”, .600” w.t., QRL
Kick-off Location: Ozona, TX
End of Survey: Brackettville, TX
Start Date: November 2018
Completion Date: July 2019
Construction Duration: 8 Months